Three weeks before go-live on a lab expansion, everything looks on track—until someone asks who approved the acceptance criteria for the environmental monitoring study. Engineering, validation, and quality each assumed someone else owned it. That scenario opened Nathan Roman's session at Lab Manager's 2026 Quality & Compliance Digital Summit. Roman, founder and principal of Validation Management Solutions (VMS) and author of Six Steps to Effective Temperature Mapping, has spent more than 25 years in commissioning, qualification, and validation (CQV) for pharmaceutical, biotech, and medical device organizations. His core message to lab leaders: growth rarely stumbles on the science, but in the seams between teams. The remedy is building quality into laboratory operations from the outset.

Nathan Roman, founder and principal of Validation Management Solutions (VMS).
Why do lab expansion projects break down?
Roman was careful to note that the opening scenario wasn't a story about incompetence; it was a failure of scale. "The gap wasn't in the work," he said. "It was in the space between the work, where one team ends and another begins."
As a lab grows, informal controls, such as a spreadsheet maintained by one person, an unwritten calibration schedule, or verbal approvals, quietly break down. "Nobody's decided to remove the controls," Roman explained. "You just outgrew them without noticing."
Across every project he has supported, from lab moves to pilot plant startups, one pattern holds. "Most delays are not caused by bad science," he said. "They're caused by quality and validation entering the conversation too late."
The cost of late laboratory validation
When specifications aren't locked, validation operates in what Roman calls reaction mode, forcing teams to fix reality on the fly rather than shaping what "good" looks like upfront. "You can't prove a system meets its requirements if nobody's agreed on what the requirements are," he noted.
He shared a project that made the cost painfully concrete. The site only recognized it would need significant validation spend after the new year, once the project was underway. With no validation line item in the budget, Roman's team was formally told to stop work while funding was sorted out. The lab sat fully built, equipment in place, timeline slipping. The organization paid twice: once in unplanned spend, and again in delay and rework.
Validation costs don't look like equipment—they look like time, protocols, and review cycles—so they slip off the capital plan. His lesson: "The cheapest moment to account for validation is the moment you're already spending money on everything else around it."
When should validation get a seat at the table?
Validation must be involved in downstream-shaping decisions:
Equipment selection: Confirming a system can meet the actual tolerance and data requirements.
Site planning: Accounting for installation and environmental conditions.
Acceptance criteria: Defining success metrics before purchases are made.
Commissioning strategy: Designing testing so its evidence carries forward.
"Early validation isn't a cost center," Roman said. "It's insurance against the most expensive kind of delays."
During the session, an attendee asked whether this applies to smaller labs. Roman argued it matters more, since small labs have less margin to absorb mistakes. Early involvement doesn't have to be extensive. Even for small labs, 15 minutes of early validation consulting, asking how a system will be proven to work and what auditors will expect, can prevent costly project stalls.
Early warning signs that a lab has outgrown its systems
Trouble rarely announces itself, but Roman pointed to operational red flags lab leaders should watch for:
Duplicate work: The same reviews happen repeatedly.
Expert bottlenecks: Subject matter experts become choke points.
Coordination overload: Teams spend more time coordinating than executing.
Stalled momentum : Everyone is genuinely busy, yet progress slows.
At that point, "this isn't a workload problem. It's a systems problem," Roman explained. When these occur, hiring staff to a broken process only worsens coordination. "Adding staff to a clarity problem is like adding lanes to a road with no signs," he said. The solution is clarifying ownership, standardizing documentation, and making the work visible.
Clarifying ownership with shared language
In Roman's experience, most growing labs "don't have a people problem. They have a clarity problem." Fixing it often starts with shared vocabulary, because teams use the same words to mean different things. Roman recommends adopting these standard definitions lab-wide: "Calibration is about the instrument. Qualification is about the equipment. And validation is about the process." Or, at the bench: "A thermometer gets calibrated. The incubator gets qualified. And the method that runs in that incubator gets validated."
With the language settled, ownership aligns cleanly:
Validation: Owns the strategy, scope, and acceptance criteria.
Engineering: Owns installation and functional execution.
Operations: Defines intended use and workflows.
Quality: Aligns early on risk and compliance decisions.
Roman noted that regulators and industry bodies, including the FDA, EMA, and ISPE, emphasize clear accountability for validation. In practice, Roman said, one person should ultimately own the validation decision, whether that's a validation lead, a process owner, or a quality head. A simple responsibility map, or RACI, makes that tangible. "The magic isn't in the grid of the RACI," he said. "The magic's in that conversation you're forced to have to fill it in."
Adopting a risk-based approach to testing
High-performing teams stop treating validation as a finish line activity. Consider a familiar example: engineering performs a functional test during commissioning, then validation repeats essentially the same test during operational qualification (OQ). Integrated commissioning and qualification aligns that work from the beginning, so engineering data is captured in a form validation can use. Roman's mindset: "Test once, not twice." This isn't about cutting corners, he stressed. It's "the same rigor, half the redundant effort."
Repeatability follows the same logic. When qualifying identical equipment models, Roman recommends modular documentation, reusable approved protocols, and, in many cases, an SOP-based equipment qualification approach rather than a full IOQ package for every unit.
The key for auditors is documented rationale. Site-specific factors such as installation, utilities, and location are verified every time, while proven performance under equivalent use and risk carries forward. "What makes them nervous isn't reuse," Roman said. "It's reuse with no written justification behind it."
Building a scalable quality culture
Without structure, compliance turns reactive, and in a fast-growing lab that becomes audit risk quickly. Roman's guidance for building a quality culture includes:
Make the work visible: "Scalability requires visibility, not just more documents," Roman said. Teams must know what is in progress, what is overdue, and which version is current.
Watch for quality fatigue: When staff follow templates without understanding the intent, deviations climb. "Quality fatigue is dangerous precisely because it's invisible on paper," he noted.
Teach the “why”: Personnel who understand the reasoning behind a procedure can safely navigate situations the SOP didn't anticipate.
Test for culture, not compliance: "If your quality only holds together when an audit is coming, it's not yet culture. It's a fire drill."
Roman argued that audit readiness shouldn't be measured by inspection outcomes alone, but by whether a lab can keep growing without exhausting its best people. As he concluded, "The fastest teams usually aren't the ones working the hardest. They're the ones that built quality into their operations from the start."